Northwest Transmission Line
2013 PHASE 1
Construction of a 287 kV transmission line that spans remote mountainous terrain from Terrace to the Bob Quinn airstrip in British Columbia.
​
RDL’s Role:
-
Drill and install guy anchors and concrete foundations for towers from Terrace,BC to Bob Quin Lake utilizing multiple heli portable drill units to complete micro piling and guy anchor installations.
​


NTL job 2

Foundation Structure grout form